Project Scheduling Using
State-based Probabilistic Decision Network s
|
ABSTRACT This paper presents probabilistic CPM scheduling using an add-on program to the STROBOSCOPE simulation system that allows dependence and correlation between activity durations as well as control over precedence and the selection of paths. Activity durations and sequencing can be defined in terms of the dynamic information that becomes available as a project evolves and includes the actual start date and duration of activities already started. An example highway project illustrates the modeling power of this approach.
| AUTHORS Photios G. Ioannou
Civil & Environmental Engineering Department University of Michigan Ann Arbor, Michigan 48109-2125, U.S.A. e-mail: photios@umich.edu Julio C. Martinez Charles E. Via, Jr. Department of Civil Engineering Virginia Tech Blacksburg, Virginia 24061-0105, U.S.A. e-mail: julio@vt.edu KEYWORDS STROBOSCOPE, highway, construction, simulation, modeling , animation, activity scanning, CPM, PERT, probability, scheduling. AVAILABILITY Ioannou, P.G., Martinez, J.C., "Project Scheduling Using State-based Probabilistic Decision Networks" Proceedings, Winter Simulation Conference 98, 1287-1295, Washington, D.C., December 13-16, 1998. |